Le Van Luong Underpass construction project is one of 6 key traffic projects licensed by xổ số miền nam Hanoi People’s Committee for construction during this social distancing period. xổ số miền nam project is being urgently constructed, workers are divided into three working shifts day and night, COVID-19 prevention is tightened as well.

Le Van Luong Underpass construction project was started in October 2020, with an investment of nearly VND 700 billion (US$30 million), expected to be completed in 18 months.

xổ số miền nam project will build a reinforced concrete underpass in xổ số miền nam direction of Lê Văn Lương-Tố Hữu Street and vice versa. xổ số miền nam underpass’s total length is 475m.
According to a report of Tien Phong Newspaper, on July 31st, , workers are urgently constructing and wearing masks to prevent COVID-19
xổ số miền nam underground sewer sectionon Le Van Luong Street towards To Huu Street has been completed and is in xổ số miền nam process of finishing xổ số miền nam road surface.
Workers are still rushing construction in order to speed up xổ số miền nam progress.
xổ số miền nam construction site is currently implementing 3 construction points, with 38 staffs, workers working all day.
xổ số miền nam project is currently building xổ số miền nam underpass, retaining wall, drainage system and xổ số miền nam items which need to be ahead of schedule before xổ số miền nam rainy season 2021.

"Le Van Luong Underpass project was one of xổ số miền nam key projects of xổ số miền nam city, aiming to resolve conflicts in intersections, reduce traffic congestion and complete xổ số miền nam traffic infrastructure of xổ số miền nam capital", said representative of FECON – one of three contractors of this project.

“xổ số miền nam project has many items located deep underground, construction is very complicated so we take advantage of dry weather to speed up xổ số miền nam process” xổ số miền nam representative added".

“Construction during xổ số miền nam epidemic period requires xổ số miền nam workers comply with xổ số miền nam regulations on prevention of COVID-19 such as wearing mask, measuring body temperature before entering xổ số miền nam site. In particular, during xổ số miền nam construction process, xổ số miền nam workers keep their distance, for difficult items, divide 2 people into one construction group”, Mr. Dang Tuan, Site Manager (SM) of this project said.

After Le Van Luong underpass is completed, xổ số miền nam intersection will have a total of 10 lanes in xổ số miền nam direction of Le Van Luong – To Huu and vice versa, instead of xổ số miền nam current 8 lanes, contributing to solving traffic conflicts at this intersection, gradually completing Hanoi transport infrastructure system.