Le Van Luong Underpass construction project is one of 6 key traffic projects licensed by trực tiếp xổ số miền bắc Hanoi People’s Committee for construction during this social distancing period. trực tiếp xổ số miền bắc project is being urgently constructed, workers are divided into three working shifts day and night, COVID-19 prevention is tightened as well.

Le Van Luong Underpass construction project was started in October 2020, with an investment of nearly VND 700 billion (US$30 million), expected to be completed in 18 months.

trực tiếp xổ số miền bắc project will build a reinforced concrete underpass in trực tiếp xổ số miền bắc direction of Lê Văn Lương-Tố Hữu Street and vice versa. trực tiếp xổ số miền bắc underpass’s total length is 475m.
According to a report of Tien Phong Newspaper, on July 31st, , workers are urgently constructing and wearing masks to prevent COVID-19
trực tiếp xổ số miền bắc underground sewer sectionon Le Van Luong Street towards To Huu Street has been completed and is in trực tiếp xổ số miền bắc process of finishing trực tiếp xổ số miền bắc road surface.
Workers are still rushing construction in order to speed up trực tiếp xổ số miền bắc progress.
trực tiếp xổ số miền bắc construction site is currently implementing 3 construction points, with 38 staffs, workers working all day.
trực tiếp xổ số miền bắc project is currently building trực tiếp xổ số miền bắc underpass, retaining wall, drainage system and trực tiếp xổ số miền bắc items which need to be ahead of schedule before trực tiếp xổ số miền bắc rainy season 2021.

"Le Van Luong Underpass project was one of trực tiếp xổ số miền bắc key projects of trực tiếp xổ số miền bắc city, aiming to resolve conflicts in intersections, reduce traffic congestion and complete trực tiếp xổ số miền bắc traffic infrastructure of trực tiếp xổ số miền bắc capital", said representative of FECON – one of three contractors of this project.

“trực tiếp xổ số miền bắc project has many items located deep underground, construction is very complicated so we take advantage of dry weather to speed up trực tiếp xổ số miền bắc process” trực tiếp xổ số miền bắc representative added".

“Construction during trực tiếp xổ số miền bắc epidemic period requires trực tiếp xổ số miền bắc workers comply with trực tiếp xổ số miền bắc regulations on prevention of COVID-19 such as wearing mask, measuring body temperature before entering trực tiếp xổ số miền bắc site. In particular, during trực tiếp xổ số miền bắc construction process, trực tiếp xổ số miền bắc workers keep their distance, for difficult items, divide 2 people into one construction group”, Mr. Dang Tuan, Site Manager (SM) of this project said.

After Le Van Luong underpass is completed, trực tiếp xổ số miền bắc intersection will have a total of 10 lanes in trực tiếp xổ số miền bắc direction of Le Van Luong – To Huu and vice versa, instead of trực tiếp xổ số miền bắc current 8 lanes, contributing to solving traffic conflicts at this intersection, gradually completing Hanoi transport infrastructure system.